Widening and improvement of MDR-40 (Dr. Bharatkar Hegade Dessai Marg) from railway overbridge Margao to Paroda of 8.5 km. length.

This project is done in four phases.

 

Improvement of existing asphalt surface of MDR-40 (Margao-Quepem) about 7.50 km to 10 km (Paroda to Karah).(Phase IV)
Cost Rs
1,42,46,450.75
Tendered Cost Rs
1,49,56,955.00
Location From ROB junction to Rawanford junction in front of Konkan railway station
Agency M/S Sousa Engineers construction Pvt. Ltd. ,P.W.D. contractor, Curpawado, Cortalim-Goa

The existing Margao-Queperm road between ROB junction to Rawanford junction is widened to four lane standard.The items of work consist of soling ,WBM,raising and fullgrout and Bituminous macadam with Bituminous concrete for the full width.Other items such as centre line, painting of dividers,speed breaker etc are also incorporated.

 

Widening and improvement of riding surface of MDR-40 (Margao-Queperm) road in a length of 4 kms from Rawanford bridge to Benabhat.(Phase II)

Cost : Rs. 2,27,58,487.00

Tendered Cost : Rs. 2,38,72,520.00

Agency: Madanant construction Pvt. Ltd.,P.W.D. contractor, Near --data not clear. 

 Widening of Blt carpet overlaying with bituminous macadam overlaying with A.C. carpet pucca gutters are provided wherever required.

 

Improvement of riding quality surface of MDR-40 (Margao-Queperm) road on a length of 3.5 kms from Benabhat in V.P. St. Jose de arial to Paroda. (Phase III)

Cost : Rs. 2,03,77,960.00

Tendered Cost : Rs. 2,13,72,631.00

Agency : Madanant construction Pvt. Ltd.,P.W.D. contractor, Near --data not clear.

Widening of Blt carpet overlaying with bituminous macadam overlaying with A.C. carpet pucca gutters are provided wherever required. 

 

Improvement of existing asphalt surface of MDR-40 (Margao-Quepem) about 7.50 km to 10 km (Paroda to Karah).(Phase IV)

Cost : Rs. 1,42,46,450.75

Tendered Cost : Rs. 1,49,56,955.00

Agency : M/S Sousa Engineers construction Pvt. Ltd. ,P.W.D. contractor, Curpawado, Cortalim-Goa

The existing Margao-Queperm road between ROB junction to Rawanford junction is widened to four lane standard.The items of work consist of soling ,WBM,raising and fullgrout and Bituminous macadam with Bituminous concrete for the full width.Other items such as centre line, painting of dividers,speed breaker etc are also incorporated.

 

Improvement and widening of road surface of S.H. No. 5

Cost Rs. 1,60,99,546.00

Tendered Cost Rs. 1,69,04,486.00

Agency M/S Sousa Engineers construction Pvt. Ltd. ,P.W.D. contractor, Curpawado, Cortalim-Goa

 Widening of Blt carpet overlaying with bituminous macadam overlaying with A.C. carpet.

 

Improvement of the riding quality of the state highway from Raia

Cost Rs. 1,64,85,801.00

Agency M/S Sousa Engineers construction Pvt. Ltd. ,P.W.D. contractor, Curpawado, Cortalim-Goa

 

Description :  Strengthening of road with 50mm bituminous macadam overlaid with 25 mm thick bituminous concrete.

 

Widening and hot mixing of the road from Bicholim to Narva in Nayem Constituency 

Cost : Rs. 142.40 Lakhs                                                                               

Location : Bicholim

Work involve widening of hot mixing of road for Bicholim to Narva

 

This is the Official Website of Public Works Department, Government of Goa, India

  • Last Modified: 15 October 2020

Visitors Counter :joomla visitors

Copyright © 2014 Public Works Department - Govt. of Goa, India. All Rights Reserved.